Renewable Energy

DTE Energy Seeks Bids for Up to 150 MW of New Michigan Solar

Renata VidalNovember 22, 20265 min read1 views

At a glance

  • The utility is running a competitive solicitation for in-state projects that must be running by mid-2030 and tie into MISO or DTE's own distribution grid.
  • DTE Energy has opened bidding for up to 150 megawatts of new solar generation located in Michigan and commercially operational by June 30, 2030, with proposals due in January 2027. The company says the projects will create construction jobs and lower its exposure to fuel prices, while the solicitation is meant to satisfy a 2025 commission settlement agreement.
Rows of ground-mounted solar panels on flat farmland at low golden-hour light, with a transmission tower and power lines on the horizon.

DTE Energy has opened a competitive solicitation for up to 150 megawatts of new solar generation built in Michigan, a step the utility says will create construction jobs, add tax revenue for host communities and save customers money on fuel.

Because solar plants do not consume fuel, DTE expects the projects to reduce its exposure to changing fuel prices over their operating lives. The company frames the procurement as part of a wider effort to keep power reliable while making the supply cleaner and more affordable.

DTE presented the projects as an investment in the state and its communities: generating energy in Michigan, it argued, lowers reliance on fuel bought elsewhere and channels new investment and tax revenue toward schools, emergency responders and other local services.

What the solicitation requires

Proposals must cover projects sited in Michigan and interconnected either to the MISO transmission system or to DTE's own distribution network. Each project has to reach commercial operation by June 30, 2030.

  • Capacity sought: up to 150 megawatts of new solar
  • Commercial operation deadline: June 30, 2030
  • Location and interconnection: Michigan; MISO transmission system or DTE distribution system
  • Proposal deadline: Jan. 19, 2027, with contracts expected in the second or third quarter of 2027

Bidders register through PowerAdvocate to obtain further information and submit offers.

Regulatory basis

The procurement is intended to meet requirements of a settlement agreement in Michigan Public Service Commission Case No. U-21662, which the commission approved on May 15, 2025.

Existing fleet and long-range plan

DTE says its wind and solar plants already generate enough clean energy to serve nearly one million homes. The company is working toward net-zero carbon emissions and says it will keep expanding its renewable portfolio while holding a balanced mix of resources to protect reliability and affordability.

Its 2026 Integrated Resource Plan sets a larger target: an additional 15 gigawatts of renewable capacity by 2042. The 150 megawatts sought in this solicitation is a small fraction of that figure, and the announcement does not detail how the remaining capacity would be procured.

The notice does not disclose expected capital cost, how many projects DTE hopes to contract, or the price it anticipates paying per megawatt-hour; those elements would emerge from the bidding process and from contracts signed in 2027. It also does not say how many construction jobs would be created or when construction would start.

Claims about fuel savings and community benefits are the company's own characterizations. The solicitation itself fixes capacity, location, interconnection and scheduling terms, and leaves the selection of winning projects to competitive bidding.

Reported by Renata Vidal, Electric Mobility Editor.